Task | Description | Status | Client | Ilabo | Objective | Files | KB article |
C - consulted R - responsible | R - responsible I - informed | ||||||
Stage 1 | Pre-implementation tasks | ||||||
1 | Determining the number of lines (or sets of machines constituting a production unit for one production/process order), the number of machines in a line, the way of working with data collection | R | I | Determining the number of required licenses and license costs | |||
| |||||||
2. Data entered into PackOS manually (order progress, downtimes, process parameters) | |||||||
2 | Expected scope of implementation: | R | I | ||||
| |||||||
2. Process parameters monitoring (pressure, temperature, etc.) [yes/no | |||||||
3. Energy monitoring: | |||||||
a. consumed [yes/no] | |||||||
b. temporary consumption for anomaly detection [yes/no] | |||||||
4. Downtimes video monitoring [yes/no] | |||||||
5. Predictive functions (estimation of the condition of machine elements, failure prediction, anomaly detection) [yes/no] | |||||||
6. People performance management [yes/no] | |||||||
3 | Determining the method of supplying the system with source data for automatic supply: | R | I | Valuation of the costs of connecting machines | |||
| |||||||
2. Is there an OPC Server in the organization collecting signals from machines [yes/no] | |||||||
3. Is there an industrial computer/pc on which OPCServer and/or LogiXGate can be installed [yes/no/not applicable] | |||||||
4. Expected delivery of an external controller by ILABO to which the CLIENT will connect sensors (eg. photocells) (LogiX DataCollectorBox) | |||||||
a. version for mounting in an existing cabinet - on a DIN rail | |||||||
b. full cabinet with power supply and fuses | |||||||
*in special cases, we can adapt to the existing method of issuing data by drivers other than the OPC standard | |||||||
4 | Determining the method of entering orders and the SKU (Material Master) file - see points 8 and 9 | ||||||
Stage 2 | Implementation | ||||||
1 | Providing information about the line topology (topology diagram including machines to be mapped in PackOS) and units for machine counters. | C | R | Configure areas, lines, and machines in PackOS. Indication of machines acting as Base (availability, performance, quantity, set production units for area & plant | |||
2 | Analysis and preparation of the network to collect data from machines and make them available to PackOS (unblocking ports if necessary) | R | C | Readiness of the infrastructure in the factory | |||
3 | Determining the access path to the OPC Server and making the computer available for LogixGate installation (and optionally OPCServer) | C | R | Installation of LogiXGate for data collection on the factory side, OPCServer configuration if not configured by the client | |||
4 | If the LogiX DataCollectorBox delivery option has been selected, installation of the delivered LogiX DataCollectorBox by the customer | R | C | LogiX DataCollector Box installation | |||
5 | Providing a list of tags/variables in OPC with a description of the meaning (or source data from drivers if ILABO configures OPCServer) | C | R | Configuration of counters and process parameters | |||
6 | Defining downtimes list & assigment to the specific OEE loss class | C | R | Configuration of downtimes list | |||
7 | Defining rules for downtimes | C | R | Configuration of downtime rules in PackOS | |||
8 | Determining how to enter the production order plan: | stage 1 - p. 4 needs to be answered first | C | R | Preparation of import rules in FlexibleImporter if p.1a is selected | ||
| |||||||
a. providing sample files | |||||||
b. using ready-made PackOS templates | |||||||
2. By integration with the PackOS API | |||||||
3. Manually | |||||||
9 | Determination of the MaterialMaster file - SKU lists along with:
Providing data to PackOS: | stage 1 - p. 4 needs to be answered first | C | R | Preparation of import rules in FlexibleImporter if p.1a is selected | ||
| |||||||
a. providing sample files | |||||||
b. using ready-made PackOS templates | |||||||
2. Manually | |||||||
10 | Defining shifts pattern (list of shifts, shifts calendar) | C | R | Defining shifts in PackOS | |||
11 | Defining automation rules: automatic start of orders from the plan, management of changeovers, defining time classification outside shifts & orders | C | R | Defining automation rules in PackOS | |||
12 | System admins list | C | R | Define system administrator accounts | |||
13 | Users list & permissions | R | I | Defining system user accounts | |||
14 | Training of key people and starting to use the system. | C | R |
Excel link