LogiX 3.5

New tags and a cleanup of problem tags

Expected manhours field

Right now expected manhours can be provided for any activity while creating it using new fields: Expected effort for order and Expected changeover effort for their related changeover.

If left empty, expected effort for order will still be filled automatically if it was properly defined in ‘Line configuration’ for SKU.

Notifications:

  • Fixes for e-mail notifications

Bugfixes:

  • Overlapping counters machines view

  • Split OEE by Order/Shift report

  • Order names clipping beyond OEE chart

  • Rounding of signals values in current machine parameters


Mobile Cockpit Improvements

  • Changeovers_enabled flag. When false:

    • Changeover duration field in new order form is hidden

    • There is no “Activate button” on order list. Instead operator see “Start” button

  • Labour_enabled flag: Specifies if “Report resources” button is visible.

  • Other fixes and improvements